Table of deliverables list, links to delivered public documents will be added as available.

Del. no.

Deliverable name

WP no.

Nature

Dissemination
level

Delivery date


D11

Project management guidelines

1

R

PU

2

D12

Periodic reports 1, 2, 3

1

R

PU

12,24,36

D13

Final report

1

R

PU

38

D21.1

Tether factory (100 m)

21

R

PU

14

D21.2

Tether factory (1 km) requirements

21

R

PU

18

D21.3

Tether factory (1 km)

21

R

PU

32

D22.1

Tether coating report

22

R

PU

17

D23.1

Tether space environment requirements

23

R

PU

8

D23.2

Tether vacuum-testing setup

23

R

PU

12

D23.3

Tether vacuum-testing results

23

R

PU

26

D24.1

Auxiliary tether report

24

R

PU

16

D31.1

Requirements specs of the tether test reels

31

R

PU

6

D31.2

Reeling test plan

31

R

PU

6

D31.3

Reeling test results

31

R

PU

9

D31.3

Reeling test results (First Amendment)

31

R

PU

9

D32.1

Requirements specs of main tether reel

32

R

PU

7

D32.2

Design description of main tether reel

32

R

PU

11

D32.3

Main tether reel test plan

32

R

PU

18

D32.4

Main tether reel test results

32

R

PU

30

D33.1

Requirements specs of auxiliary tether reel

33

R

PU

7

D33.2

Design description of auxiliary tether reel

33

R

PU

11

D33.3

Auxiliary tether reel test plan

33

R

PU

18

D33.4

Auxiliary tether reel test results

33

R

PU

30

D41

Requirements specifications of Remote Unit

41

R

PU

7

D41.2

Design description of Remote Unit

41

R

PU

13

D41.3

Remote Unit test plan

41

R

PU

20

D41.4

Remote Unit test results

41

R

PU

32

D42.1

Final report of Remote Unit power system

42

R

PU

30

D43.1

Final report of Remote Unit control and telemetry

43

R

PU

30

D44.1

Final report of Remote Unit tether jettison

44

R

PU

30

D45.1

Final report of Remote Unit gas thruster

45

R

PU

30

D46.1

Simplified FEEP design report

46

R

CO

18

D46.2

Simplified FEEP test report

46

R

PU

30

D46.3

FEEP cost assessment for industrial prod.

46

R

PU

30

D51.1

Simulator user guide

51

R

PU

30

D51.2

Report of performed runs

51

R

PU

36

D52.1

Conceptual E-sail designs

52

R

PU

3

D53.1

Failure mode and recovery strategy analysis

53

R

PU

26

D53.2

Refined design concepts

53

R

PU

32

D61.1

E-sail mission document

61

R

PU

36

D62.1

Orbit calculations supporting WP 6.1

62

O

PP

24-36

D81

Public and media outreach summary

81

R

PU

36

Nature of the deliverable is expressed by following codes:
R = Report,
P = Prototype,
D = Demonstrator,
O = Other

The dissemination level is described with the following codes:
PU = Public
PP = Restricted to other programme participants (including the Commission Services).
RE = Restricted to a group specified by the consortium (including the Commission Services).
CO = Confidential, only for members of the consortium (including the Commission Services).